Finance
Le Jeune Road Reconstruction
Renderings
Construction Photos North
Construction Photos South
MIC Terminal Access Roadways
MIC-MIA Interchange
Other MIC Area Road Projects

Projects: Roadway Improvements

Construction Progress Photos

September 1, 2007

Le Jeune Rd.South CD Southbound September Image Map

Improvements to Le Jeune Southbound CD

Improvements to Le Jeune Southbound CD


July 1, 2007

Le Jeune Rd.South CD Southbound July Image Map.

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal




June 1, 2007

Le Jeune Rd.South CD Southbound June Image Map.

Construction Work on
Le Jeune Southbound CD

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal




May 1, 2007

Le Jeune Rd.South CD Southbound May Image Map.

Bridge 8, Bridge 9 Crossing Over Tamiami Canal and Bridge 10

Bridge 8, Bridge 9 Crossing Over Tamiami Canal and Bridge 10

Bridge 7 above Construction of LeJeune Southbound CD

Bridge 7 above Construction of LeJeune Southbound CD




April 1, 2007

Le Jeune Rd.South CD Southbound April Image Map.

Bridge 9 Crossing Over Tamiami Canal, Bridge 7 & 8 on Foreground

Column from Bridge 8, Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

Bridge 9 Crossing Over Tamiami Canal, Bridge 7 on Foreground

Construction of New LeJeune Southbound CD



March 1, 2007

Le Jeune Rd.South CD Southbound March Image Map

Construction of Bridge 9 Crossing Over Tamiami Canal.

Construction of Bridge 9 Crossing Over Tamiami Canal, Bridge 7 on Foreground


February 1, 2007

Le Jeune Rd.South CD Southbound February Image Map

Construction of Bridge 9 Crossing Over Tamiami Canal, Bridge 7 on Foreground

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

January 1, 2007

Le Jeune Rd.South CD Southbound January Image Map.

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

December 1, 2006

Le Jeune Rd.South CD Southbound December Image Map.

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

Construction of Bridge 9 Crossing Over Tamiami Canal

November 1, 2006

Le Jeune Rd.South CD Southbound November Image Map.

Le Jeune CD Southbound: Construction of Pilecaps for Bridge 9A

Le Jeune CD Southbound & Northbound Construction Site

Construction of Bridge 7 Crossing Over Tamiami Canal to MIC

October 1, 2006

Le Jeune Rd.South CD Southbound October Image Map.

Le Jeune CD Southbound

Le Jeune CD Southbound; Construction of Bridge 6, Junction with Ramps M/MT

Le Jeune CD Southbound; Construction of Bridge 6

Le Jeune CD Soutnbound; Construction of Pilecaps for Bridge 9A

Le Jeune CD Southbound Construction of Junction with SR 836

Le Jeune CD Southbound; Construction of Bridge 6

September 1, 2006

Le Jeune Rd.South CD Southbound September Image Map.

From Ramp M/MT to Bridge 6; New Exit from Airport to SR 836.

Ramp M/MT connecting with Bridge 6.

Portions of Bridge 7 going over LeJeune Road; Future Connectivity with Central Station.

August 1, 2006

Le Jeune Rd.South CD Southbound August Image Map.

Construction Work on Bridge 7

Construction Work on Bridge 9; Future LeJeune Road

Construction Work on Bridge 7, Portions Over Tamiami Canal

Construction Work on Bridge 9; Future LeJeune Road

Ramp M/MT Connecting to Bridge 6

July 1, 2006

Le Jeune Rd.South CD Southbound July Image Map.

Construction of Bridge 7 over Tamiami Canal

Construction Work at LeJeune Road South CD Southbound Site

Construction Work on
Bridges 6 & 7.

Construction Work on Bridge 6

Looking North on the New LeJeune CD Southbound & Northbound

Construction Work along NW 14th Street

Looking South on the New LeJeune CD Southbound

Connection of Bridge 6 with Ramp M/MT

June 1, 2006

Le Jeune Rd.South CD Southbound June Image Map.

Construction of Bridge 7 over Tamiami Canal

Looking South on Bridges 7 & 6 connecting with LeJeune CD Southbound

Construction Work on Bridge 6

Construction of Bridge 6 with Ramp M/MT

Laying Out the Asphalt on LeJeune CD Northbound

Looking North on the New LeJeune CD Southbound & Northbound

Construction Work along NW 14th Street

May 1, 2006

Le Jeune Rd.South CD Southbound May Image Map.

Construction of Ramp M/MT to connect with Bridge 6

Construction of Ramp M/MT to connect with Bridge 6

April 1, 2006

Le Jeune Rd.South CD Southbound April Image Map.

Construction of Bridge 7: Connects 836 with Miami Intermodal Center

Construction of Bridge 6; Connects 836 with the Airport

Construction of Ramp M/MT to Connect with Bridge 6

Widening & Reconstruction of NW 14th Street

March 1, 2006

Le Jeune Rd.South CD Southbound March Image Map.

Construction of Pier for Bridge #7, Part of MTAR

Ramp P Divides into Bridge #6 to Airport & #7 to MTAR

Ramp P Divides into Bridge #6 to Airport & #7 to MTAR

Looking North at Le Jeune Southbound CD

February 1, 2006

Le Jeune Rd.South CD Southbound February Image Map.

Construction of New LeJeune Road and Bridge #7

Construction of New LeJeune Road

Ramp P Divides into Bridge #6 to Airport & Bridge #7 to MIC

Construction of New LeJeune Road, Looking North at Bridge #7

Looking North at Le Jeune Southbound CD

Bridge #6, MIA to 836 west

Construction Work on Future Ramp M/MT to Connect with Bridge #6

January 1, 2006

Le Jeune Rd.South CD Southbound January Image Map.

Portions of Bridge 7 Crossing Over LeJeune Road.

Work on Ramp M/MT to Connect with Bridge 6.

Work on Ramp M/MT to Connect with Bridge 6.

Construction Work. Piers for Bridge #6.

Underneath View of Bridge 6 and 7 Connection with LeJeune Rd.

Construction of New Le Jeune Road

Exit from Ramp P into New Alignment for Le Jeune Southbound

Looking North at LeJeune Southbound CD.

Widening & Reconstruction of NW 14th Street

Widening & Reconstruction of NW 14th Street

December 1, 2005

Le Jeune Rd.South CD Southbound December Image Map.

Drainage Work on Future Ramp M/MT

Future Ramp M/MT: Connection between Central Blvd & Bridge 6

Bridge 7:Connection to MTAR, Bridge 6: Airport to 836 West

Bridge 6: Airport to 836 West

Portions of Bridge 7 Crossing Over LeJeune Road.

Portions of Bridge 7 Crossing Over LeJeune Road.

Construction of Bridge 6

Looking North at LeJeune Southbound CD.

Widening & Reconstruction of NW 14th Street

November 1, 2005

Le Jeune Rd.South CD Southbound November Image Map.

Work on Ramp M/MT to Connect with Bridge 6.

Bridge 6 looking towards connection with Ramp M/MT at Central Blvd.

Work on Ramp M/MT to Connect with Bridge 6.

Looking South Towards Connection of Bridges 7 & 6 with Ramp "P".

Ramp "P" Looking North at LeJeune Southbound CD

Widening and Reconstruction of NW 14th Street

October 1, 2005

Le Jeune Rd.South CD Southbound October Image Map.

Work on Future Ramp M/MT

Work on Future Ramp M/MT.

Future Bridge #6 Central Blvd. to 836 West

Construction Material Layed Along Future LeJeune Road.

Construction of Deck Slab for Bridge 6

Reconstruction of NW 14th Street

Drainage Work Along NW 14th Street

September 1, 2005

Le Jeune Rd.South CD Southbound September Image Map.

Construction Material at LeJeune South CD Southbound Site.

Work on Future Ramp M/MT.

Work on Future Ramp M/MT.

Work on Future Ramp M/MT.

Improvements on LeJeune Road.

Future Bridge #6 Central Blvd. to 836 West.

Ramp "P" Looking North at LeJeune Southbound CD.

August 1, 2005

Le Jeune Rd. Southbound August Image Map

Anchors placed for Future Ramps M & MT.

Reconstruction of NW 14th Street

Future Bridge #6 Piers to Connect with Central Boulevard

Future Bridge #6 Piers to Connect with Central Boulevard

Placement of End Bents for Future Ramps M and MT

Construction of Bridge 6, Ramp and End Bents

July 1, 2005

Construction along Future LeJeune Road Site

Infrastructure Drainage Construction

Future Bridge #6 Piers to connect with Central Boulevard

Placement of End Bents for Future Ramp M and MT

Placement of Anchors for Future Ramp M and MT

Construction Material laid out for Drainage Work along LeJeune Rd.

June 1, 2005

LeJeune Road South CD Southbound Project
June 2005 Image Map

View of Ramp P from Le Jeune Road

Bridge 6 Piers

Placement of End Bents for Future Ramp M and MT

Ramp O and Ramp P looking North at Le Jeune Southbound CD

Drainage Work along Le Jeune Road

May 1, 2005

View of Project from Central Blvd.

Close Up of Ramp P Exit to LeJeune Southbound and 836 West

Ramp M & MT Work, Soil Test and Anchors Being Placed

Ramp M & MT Work, Soil Test and Anchors Being Placed

April 1, 2005

LeJeune Road South CD Southbound Project
April 2005 Image Map

Exit from Ramp P into New Alignment for LeJeune Southbound

Construction of Ramp L exiting from Bridge 6

Foundation Footing for Bridge 6 Piers

March 1, 2005

LeJeune Road South CD Southbound Project
March 2005 Image Map

Foundation Footing for Bridge 6 Piers

First Concrete Pour at Bridge 6 Piers

First Concrete Pour at Bridge 6 Piers

Ramp P to 836 East and Le Jeune Rd. Southbound

Close Up of Ramp P Exit to Le Jeune Southbound and 836 West

Ramp O and Ramp P Looking North at Le Jeune Southbound CD

Stabilizing Concrete of Foundation Footing for Bridge 6

February 1, 2005

LeJeune Road South CD Southbound Project
February 2005 Image Map

Future Bridge 6

Ramp M to connect with
Bridge 6

Future Bridge 6

LeJeune Road South CD Southbound Project

Future Le Jeune Road

Ramp M to connect with Future Bridge 6

Construction of Future Bridge 6

LeJeune Road South CD Southbound Showing Ramps M & O

January 1, 2005

LeJeune Road South CD Southbound Project

Lightpoles Installed on Pilasters at MSE Wall

Bridge Lighting System

Future Retention Pond

December 1, 2004

LeJeune Road South CD Southbound Dec 2004. Image Map

Lightpole Pilasters at MSE Wall

Finishing Details at MSE Wall

LeJeune Road South CD Southbound Dec 2004 Aeial

November 1, 2004

LeJeune Road South CD Southbound Nov. Image Map

MSE Retaining Wall Roadway Embackment

Roadway Embackment and Drainage Outlet at MSE Wall

Construction of Lightpole Pilasters at MSE Wall

October 1, 2004

LeJeune Road South CD Southbound Oct. Image Map

NW 14th Street Bridge Construction at Le Jeune Rd. South CD Southbound

Traffic Railing Barrier along MSE Wall

Earth work at Le Jeune Road South CD Southbound

September 1, 2004

LeJeune Road South CD Southbound Sept. Image Map

MSE Wall at Le Jeune Rd. South CD Southbound

NW 14th Street Bridge Construction at Le Jeune Rd. South CD Southbound

Earth work along Le Jeune Road South CD Southbound

Construction of Drainage Outlet

Earth work at Le Jeune Road South CD Southbound

Traffic Railing Barrier along MSE Wall

Drainage Outlet at MSE Wall

July 1, 2004

LeJeune Road South CD Southbound Image Map

MSE Retaining Wall at 14th Street Bridge (North Side)
July 2004

MSE Retaining Wall in Front of Bridge End Bent at 14th Street (South Side)
July 2004

Close-up of MSE Retaining Wall in Front of Bridge End Bent at 14th Street (South Side)
July 2004

MSE Retaining Wall Along NW 42nd Court
July 2004

MSE Retaining Wall Along NW 42nd Court
July 2004

Construction of MSE Retaining Wall Along NW 42nd Court
August 2004

MSE Retaining Wall Along NW 42nd Court
August 2004



Site Map  |    Powered by Panther